The cement mixers were there. The sockets are now ready and hardened. A big step has been taken. In the next few days, the first deliveries for the steel tower are expected.

Overlay

From the end of March to the middle of May, the foundation and foundation work for the Vertical Sky® A 32 certification system continued on the Grevenbroich wind test field. The filling of about 44 truck mixers was necessary to pour the foundations with concrete..

20190514_145656_resized_1-692.jpg

Aligned and pre-filled with contact cement for the first part of the lattice tower.

the base works are soon completed
Overlay
base 2 is filled
Overlay
five workers filled the crane foundation with concrete, two truck mixers drove backwards to the foundations, the workers attach the pipes to the truck mixer
Socket two is poured out, the bevel is reflected like a snowfield between the mounds

Three of the foundations look like this. They are smaller and have a bevel at the foot in the upper area. After mounting the first lattice mast part, the reinforcement is completed and the head is concreted.

Overlay
The crane foundation is larger than the pedestals, reinforcements protrude from the concrete, right four heaps with further reinforcements are stacked on the concrete, the earth around the foundation is rolled flat.

The crane foundation will not be beveled. It will stay that way in the foot area. Again, the reinforcement is completed only when the first part of the lattice tower is mounted. For the lattice mast and the crane two heads are provided.

Overlay
The concreting work is over. The paths are prepared. Everything is flat, there are no more mounds. Everything is tidied up for the next stage of construction and the crew of the steel tower.

The construction site is ready for a shift change. The team for the steel tower take over the construction site.